In July 2023 Lucara Diamond told the market that the underground expansion at its Karowe mine would now cost $683 million at completion, a 25 per cent increase on the May 2022 estimate. Grouting through water-bearing sandstone had taken longer than planned and construction would run 28 per cent longer. The company said the $136 million rise was "predominantly related to increased schedule duration and related labour costs". It put about 20 per cent of the increase down to grouting costs, which it said had been funded through contingency. The forecast still carried unallocated contingency of $49.3 million, 12 per cent of the $419 million left to spend.

The release doesn't say what that contingency was built to cover. So I draw no conclusion about Lucara's. My point is general, and it carries to any build where ground or productivity sets the pace. When time is what moves the cost, a contingency with no allowance for delay gives the board no early warning.

The Project Team Marks Its Own Numbers

Every number a board uses to judge contingency comes from the team spending it. That team reports the drawdown. It also reports the per cent complete and decides which variations count as pending. It usually picks the timing of the risk model re-run too. So the board reads numbers the project team controls.

A good owner's controls manager already plots drawdown against progress every month. The trouble is that per cent complete is the softest number on the page, and every input that would show a problem early sits with the same team, and they'd rather solve it first. An outside check helps only if it reports to the board and had no hand in preparing the numbers it tests. A lender's independent engineer reports to the lender. The board needs its own read.

A Balance Needs a Floor to Be Read Against

The US Federal Transit Administration's Oversight Procedure 40 (OP 40, March 2022) has sponsors set contingency drawdown curves as minimums. Appendix M lists levels of contingency it calls prudent, as a share of the estimate at completion without contingency: 20 per cent before bids, 13 per cent at construction start, 9 per cent at 20 per cent construction complete and 7 per cent at 50 per cent (Exhibit 1). Remaining contingency is compared with those minimums, and the sponsor's plan says what happens when it crosses one.

The FTA contingency floor falls to 7 per cent when half builtThe US Federal Transit Administration's minimum contingency for US transit projects at P65, allocated and unallocated together, falls from 20 per cent of the estimate at completion without contingency before bids to 13 per cent at construction start, 9 per cent at 20 per cent complete and 7 per cent at 50 per cent complete. EXHIBIT 1 The FTA contingency floor falls to 7 per cent when half built Minimum contingency, allocated and unallocated together, % of the estimate at completion without contingency 20% Before bids 95% design 13% Construction start 9% Construction 20% complete 7% Construction 50% complete Note: The FTA sets these minimums for US transit projects at P65, a 65 per cent confidence level. A mine owner should set its own floor from its own risk model. Source: US Federal Transit Administration, OP 40 Risk and Contingency Review (March 2022), Appendix M.
Exhibit 1 Data
Exhibit 1. The FTA contingency floor falls to 7 per cent when half built. Minimum contingency, allocated and unallocated together, as a percentage of the estimate at completion without contingency. The FTA sets these minimums for US transit projects at P65, a 65 per cent confidence level. A mine owner should set its own floor from its own risk model. Source: US Federal Transit Administration, OP 40 Risk and Contingency Review (March 2022), Appendix M.
StageMinimum Contingency (% of Estimate at Completion Without Contingency)
Before bids (95% design)20
Construction start13
Construction 20% complete9
Construction 50% complete7

The curve is a floor, and a project can spend down to it. Below it, the sponsor acts. Those are transit figures at P65, and a mine owner should set its own floor from its own risk model at the financing decision. If the board hasn't seen one, it can't read the balance.

An illustration, with made-up round numbers. Two projects start construction with $400 million of base cost and $60 million of contingency, 15 per cent and above the FTA's 13 per cent floor. This month both report $35 million left. Each has drawn $25 million into its base, which is now about $425 million.

Project A is 50 per cent complete. The 7 per cent floor on $425 million is about $30 million, so A is above it. Project B is 20 per cent complete. Its 9 per cent floor is about $38 million, so B is below it, with four fifths of the build to go. Both board papers show the same $35 million, and one of these projects needs action this month.

Schedule Risk Is Usually Missing From the Contingency

OP 40 gives time its own cover. Schedule contingency sits on a separate curve beside the cost curve, and at each future milestone it should be enough to absorb a delay of 25 per cent of the remaining non-contingency schedule.

In my view the item most often left out of a mining cost contingency is the cost of delay. On junior and mid-tier builds I'd expect the risk register to price events and estimate ranges with the duration held fixed. AACE International's risk analysis guide (PGD 02) treats cost growth and schedule slip as both quantified in contingency analysis, and the Australian Government's Supplementary Guidance Note 3A (November 2023) uses a "duration risk factor" to drive overheads and the other time-related costs.

Take the illustration again and say time-related costs run at $2 million a month. A six-month slip on Project A takes $12 million, leaving $23 million against a floor that's grown to about $31 million. A goes from comfortable to short without a single new risk event (Exhibit 2).

A six-month slip takes Project A from above its floor to shortIllustrative: both projects report $35 million left, Project B at 20 per cent complete is about $3 million below its 9 per cent floor of about $38 million, Project A at 50 per cent complete is about $5 million above its 7 per cent floor of about $30 million and a six-month slip at $2 million a month leaves A with $23 million against a floor of about $31 million, about $8 million short. EXHIBIT 2 ILLUSTRATIVE A six-month slip takes Project A from above its floor to short Contingency left (dot) against the floor (vertical mark), $ million. Both projects report the same $35 million left. $20m $25m $30m $35m $40m Project B 20% complete $35m left 9% floor about $38m About $3m short Project A 50% complete $35m left 7% floor about $30m About $5m above Project A after a six-month slip at $2m a month $23m left 7% floor about $31m About $8m short Note: Illustrative. $400m base and $60m contingency at construction start, $25m drawn into base. Floor is the FTA rate for US transit at P65 times cost without contingency; the slip adds $12m to cost and takes $12m from contingency. Source: Illustration, not a real project. Floor rates from US Federal Transit Administration, OP 40 Risk and Contingency Review (March 2022), Appendix M.
Exhibit 2 Data
Exhibit 2 (illustrative). A six-month slip takes Project A from above its floor to short. Contingency left against the floor, $ million, made-up round numbers; both projects report the same $35 million left. Floor is the FTA rate for US transit at P65 times cost without contingency. Source: illustration, not a real project; floor rates from US Federal Transit Administration, OP 40 Risk and Contingency Review (March 2022), Appendix M.
CasePer Cent CompleteContingency Left ($m)Floor ($m)Position
Project B2035About 38 (9% of 425)About 3 short
Project A5035About 30 (7% of 425)About 5 above
Project A after a six-month slip at $2m a month5023About 31 (7% of 437, the base after the slip adds 12)About 8 short

Patterns and What Each One Means

OP 40 measures allocated and unallocated contingency together. Lucara's release reports the unallocated figure. On any project, contingency moved early into package budgets can leave the unallocated line looking healthy after most of the cover has gone.

Drawdown that keeps running ahead of plan after the major packages are let usually means a light estimate or unready design. That's my reading. McKinsey's November 2024 analysis found that about two-thirds of cost overruns and schedule delays "could be attributed to poor initial assessments".

A flat line followed by a cliff is a reporting problem first. Pending variations and unresolved claims sit outside the ledger until someone has to book them.

Scope growth gets charged to contingency too. AACE's terminology standard, 10S-90, as reproduced in PGD 02, says contingency "usually excludes" major scope changes such as "changes in end product specification, capacities". In my view the request often comes late from the owner's operations side, and the board pays for new scope without being asked.

Re-Run the Model on What's Happened

Note 3A, written for project development, asks for the analysis to be "continuously reviewed and updated as more data become available". During delivery that means re-running the Monte Carlo on actual productivity and ground conditions. Retired risks come out, and any risk that has happened goes in at what it's cost so far.

If the re-run shows the budget you set at P80 now has only about an even chance of holding, the board needs to hear it that month. A worse number mid-build brings disclosure questions. That's the reason to re-run early and on a fixed timetable, so the board meets the number on its own schedule.

Three Questions on the Contingency

  • Does the contingency carry the cost of delay?
  • What's left once pending variations and open claims are netted off?
  • When was the risk model last re-run on actual performance?