Insights
Questions Before Capital
What I'd want a board to ask before it commits capital. The papers work through real cases from the public record.
Featured Paper | 19 November 2026
Contingency Drawdown as an Early Warning
Browse by Theme
Four themes hold a paper or an explainer today. A theme appears here once it holds one.
The Papers
-
Sponsors were told Tier 1 programmes, added together, would end in 2020 Paper19 November 2026 | Independent Checks
Not Marking Your Own Work
The question it asksWho checked this estimate, and who appointed them?
-
AACE's Class 3 high end runs further than its low end Paper19 November 2026 | Estimates
The Plus or Minus on the Cover
The question it asksWas the quantitative risk analysis run on this estimate, or was a factored range applied after it was finished?
-
The FTA contingency floor falls to 7 per cent when half built Paper19 November 2026 | Contingency
Contingency Drawdown as an Early Warning
The question it asksDoes the contingency carry the cost of delay?
Explainer | Try It
Move the Confidence Level
A P50 cost is the figure the project has an even chance of coming in under. A P80 cost is the figure it has an eight in ten chance of coming in under. Both are readings off one model of the project.
P80
An 80 in 100 chance the final cost comes in under this figure.
- Illustrative cost, where P50 is 100
- 119
- Gap above the P50
- 19
Illustrative. Both cost ranges are invented for this explainer and the figures are index numbers, with the P50 set at 100. On a real project the range comes from your own estimate, schedule and risk register.
Drag on the chart, or use the slider or the arrow keys.
The Explainers
Short pages on the terms the papers use, each with what to ask.
-
Explainer11 November 2026 | Contingency
P50 and P80
A P50 and a P80 are two readings off one model of the project. A board reading both can see how wide the range of outcomes still is.
What to askWhich number is the budget, and which number is the board being asked to approve?
-
Explainer11 November 2026 | Contingency
Contingency
Contingency is money held for costs that are already in the estimate's scope but can't yet be priced. A flat percentage is the same figure whatever the project's risks.
What to askHow was the figure derived, and what confidence level is it set at?
-
Explainer11 November 2026 | Capital Decisions
Decision Gates
The people at a gate need written criteria and the authority to stop the project or send it back.
What to askWho can stop the project or send it back, and has that ever happened?
-
Explainer11 November 2026 | Estimates
Basis of Estimate
The basis of estimate sets out what a cost estimate is built on. A reviewer works from it to test the estimate's assumptions.
What to askIs there a written basis of estimate, and is it current?
The Question Each Paper Asks
-
Who checked this estimate, and who appointed them?
From the paper Not Marking Your Own Work
-
Was the quantitative risk analysis run on this estimate, or was a factored range applied after it was finished?
From the paper The Plus or Minus on the Cover
-
Does the contingency carry the cost of delay?
From the paper Contingency Drawdown as an Early Warning

For the Project Team
Take the Project Check
Five questions on where your project stands, with the result on screen and nothing stored on this website.