Insights

Questions Before Capital

What I'd want a board to ask before it commits capital. The papers work through real cases from the public record.

Read the PapersTry the P50 and P80 Explainer

Featured Paper | 19 November 2026

Contingency Drawdown as an Early Warning

The FTA contingency floor falls to 7 per cent when half built From the paper Contingency Drawdown as an Early Warning. Minimum contingency, allocated and unallocated together, % of the estimate at completion without contingency. The FTA sets these minimums for US transit projects at P65, a 65 per cent confidence level. A mine owner should set its own floor from its own risk model. Source: US Federal Transit Administration, OP 40 Risk and Contingency Review (March 2022), Appendix M.
Read the Paper

The Papers

  • Timeline from 2018 to the end of 2020 Timeline from 2018 to the end of 2020. February 2018: sponsors are told the programmes, added together, would end in 2020. August 2018: the December 2018 opening is called off. The year 2020 is highlighted. February 2018: sponsors told 2020 December 2018: planned opening August 2018: opening called off 2020 20182019end 2020
    Sponsors were told Tier 1 programmes, added together, would end in 2020

    Paper19 November 2026 | Independent Checks

    Not Marking Your Own Work

    The question it asksWho checked this estimate, and who appointed them?

  • AACE Class 3 against an illustrative cover range Range bars on a scale marked at 20 per cent under, 0 and 20 per cent over, with 0 marked. AACE Class 3 at 80 per cent confidence: low end 10 to 20 per cent under, high end 10 to 30 per cent over. Illustrative cover range: plus or minus 15 per cent. AACE Class 3, at 80% confidence Low end High end: +10% to +30% Illustrative cover range: plus or minus 15% 20% under020% over
    AACE's Class 3 high end runs further than its low end

    Paper19 November 2026 | Estimates

    The Plus or Minus on the Cover

    The question it asksWas the quantitative risk analysis run on this estimate, or was a factored range applied after it was finished?

  • Minimum contingency falls as the project is built Bar chart of minimum contingency: 20 per cent before bids, 13 per cent at start, 9 per cent at 20 per cent built and 7 per cent at 50 per cent built, the last bar highlighted. 20%13%9%7% Before bidsStart20% built50% built
    The FTA contingency floor falls to 7 per cent when half built

    Paper19 November 2026 | Contingency

    Contingency Drawdown as an Early Warning

    The question it asksDoes the contingency carry the cost of delay?

Explainer | Try It

Move the Confidence Level

A P50 cost is the figure the project has an even chance of coming in under. A P80 cost is the figure it has an eight in ten chance of coming in under. Both are readings off one model of the project.

P80

An 80 in 100 chance the final cost comes in under this figure.

Illustrative cost, where P50 is 100
119
Gap above the P50
19

Illustrative. Both cost ranges are invented for this explainer and the figures are index numbers, with the P50 set at 100. On a real project the range comes from your own estimate, schedule and risk register.

Drag on the chart, or use the slider or the arrow keys.

The Explainers

Short pages on the terms the papers use, each with what to ask.

  • Explainer11 November 2026 | Contingency

    P50 and P80

    A P50 and a P80 are two readings off one model of the project. A board reading both can see how wide the range of outcomes still is.

    What to askWhich number is the budget, and which number is the board being asked to approve?

  • Explainer11 November 2026 | Contingency

    Contingency

    Contingency is money held for costs that are already in the estimate's scope but can't yet be priced. A flat percentage is the same figure whatever the project's risks.

    What to askHow was the figure derived, and what confidence level is it set at?

  • Explainer11 November 2026 | Capital Decisions

    Decision Gates

    The people at a gate need written criteria and the authority to stop the project or send it back.

    What to askWho can stop the project or send it back, and has that ever happened?

  • Explainer11 November 2026 | Estimates

    Basis of Estimate

    The basis of estimate sets out what a cost estimate is built on. A reviewer works from it to test the estimate's assumptions.

    What to askIs there a written basis of estimate, and is it current?

The Question Each Paper Asks

  1. Who checked this estimate, and who appointed them?

    From the paper Not Marking Your Own Work

  2. Was the quantitative risk analysis run on this estimate, or was a factored range applied after it was finished?

    From the paper The Plus or Minus on the Cover

  3. Does the contingency carry the cost of delay?

    From the paper Contingency Drawdown as an Early Warning

For the Project Team

Take the Project Check

Five questions on where your project stands, with the result on screen and nothing stored on this website.

Take the Project Check