A gold or lithium board approving a build takes its read on the cost and the date from the people delivering it. A London railway left a detailed public record of what that can do.

At the February 2018 Sponsor Board, Crossrail Ltd's then Programme Director told the sponsors that the handover schedule "has always been ambitious and intended to drive behaviour". He also told them that "if all the Tier 1 contractors' programmes were simply added together the programme would end in 2020". The UK National Audit Office records both remarks in its May 2019 report, and it records that Crossrail Ltd and the sponsors kept their focus on the December 2018 opening date (Exhibit 1). In August 2018 Crossrail Ltd announced the central section wouldn't open that December.

Sponsors were told Tier 1 programmes, added together, would end in 2020 Timeline from January 2018 to December 2020. February 2018: the Programme Director told the Sponsor Board that the Tier 1 contractors' programmes, simply added together, would end in 2020. August 2018: Crossrail Ltd announced the central section would not open in December 2018. December 2018: the planned opening date, held in focus by Crossrail Ltd and the sponsors until August. 2020, highlighted: drawn as a band across the whole year, because the source gives the year only. Source: National Audit Office, Completing Crossrail, May 2019, paras 2.20 and 2.26 and summary para 3. EXHIBIT 1 Sponsors were told Tier 1 programmes, added together, would end in 2020 Crossrail central section, events in the NAO record by month, 2018 to 2020 2018 2019 February 2018 Sponsor Board The Programme Director tells the sponsors the Tier 1 contractors' programmes, simply added together, would end in 2020 December 2018 Planned opening date, held in focus until August 2020 Tier 1 programmes, simply added together, would end August 2018 Crossrail Ltd announces the central section won't open that December Note: Crossrail Ltd and the sponsors kept their focus on December 2018. The source gives 2020 as a year only, so the whole year is shaded. Source: National Audit Office, Completing Crossrail (May 2019), paras 2.20 and 2.26; summary para 3.
Exhibit 1 Data
Exhibit 1. Sponsors were told Tier 1 programmes, added together, would end in 2020. Crossrail central section, events in the NAO record by month, 2018 to 2020. Note: the sponsors were told the Tier 1 programmes, simply added together, would end in 2020; Crossrail Ltd and the sponsors kept their focus on December 2018; the source gives 2020 as a year only. Source: National Audit Office, Completing Crossrail (May 2019), paras 2.20 and 2.26; summary para 3.
DateEvent
February 2018At the Sponsor Board the Programme Director tells the sponsors the Tier 1 contractors' programmes, simply added together, would end in 2020
August 2018Crossrail Ltd announces the central section won't open in December 2018
December 2018Planned opening date, held in focus by Crossrail Ltd and the sponsors until August
2020 (year only)Where the Tier 1 contractors' programmes, simply added together, would end

The NAO also found that throughout the programme, progress reports to the Crossrail Ltd board and sponsors put the emphasis on "what had been achieved and how much of the programme had been completed, rather than on the level of risk to successful delivery that remained in the programme".

Crossrail had an outside check. The NAO lists a sponsors' Project Representative, Jacobs, "Embedded in CRL", which "Reports on progress to sponsor team and carries out specific investigations at sponsors' request". On the handover schedule, the NAO found "a set of more or less separate plans" and "the absence of an integrated, realistic plan". The report doesn't say whether the Project Representative raised the schedule before August, so I won't guess. During 2018 the sponsors commissioned three KPMG reviews.

Whether a different check would have saved the date can't be known from the record. The record shows two different jobs. A progress report tells the sponsors what's been done. Finding out how long the rest will take means testing the remaining programme itself. A board should know which one it's buying.

Two Kinds of Pressure

In my view the sponsor, the Project Director and the EPCM all have a stake in the answer to the one question the board most needs answered. Flyvbjerg and two co-authors, in the California Management Review in 2009, put deliberate misforecasting, which they call deception, down to "the different preferences and incentives of the actors".

The EPCM's position is set by its contract. The Project Director's pressure comes from above. A Project Director signs the forecast and reports to an executive who championed the project. Walking that forecast back means putting their own name to the bad news. When a board thanks the Project Director for green reports and cross-examines whoever brings a red one, the next Project Director learns to report green for as long as they can.

The Owner Carries Most of the Cost Risk

A 2014 Mining Journal note by Shearman & Sterling (now A&O Shearman) says the EPCM contractor "typically receives compensation on a cost-plus basis" and the owner "bears most, if not all, the risk of inflated project costs". PwC's 2016 guide to EPCM contracts says the EPCM contractor's maximum liability "is often limited to the re-performance of defective services" and capped at between 5 and 20 per cent of its total remuneration (Exhibit 2). The guide adds that some EPCM contractors are unwilling to put a material percentage of their remuneration at risk on a KPI incentive regime.

EPCM liability is often capped at 5% to 20% of remuneration A bar shows the EPCM contractor's total remuneration from 0 to 100 per cent. A segment from 5 to 20 per cent shows that the maximum liability cap often falls between 5 and 20 per cent. The owner bears most, if not all, the risk of inflated project costs. Sources: PwC Australia, EPCM Contracts, January 2016, page 5; Shearman and Sterling, One way, or another, Mining Journal, 18 April 2014. EXHIBIT 2 EPCM liability is often capped at 5% to 20% of remuneration Maximum liability of an EPCM contractor, per cent of its total remuneration The cap often falls between 5% and 20% Total EPCM remuneration 5% 20% 0% 50% 100% Note: The owner bears "most, if not all, the risk of inflated project costs". Source: PwC Australia, EPCM Contracts (January 2016), p. 5; Shearman & Sterling, "One way, or another", Mining Journal (18 April 2014).
Exhibit 2 Data
Exhibit 2. EPCM liability is often capped at 5% to 20% of remuneration. Maximum liability of an EPCM contractor, per cent of its total remuneration. Source: PwC Australia, EPCM Contracts (January 2016), p. 5; Shearman & Sterling, "One way, or another", Mining Journal (18 April 2014).
PartyExposure
EPCM contractorMaximum liability often capped at between 5 and 20 per cent of total EPCM remuneration
OwnerBears most, if not all, the risk of inflated project costs

Under those terms a design error that reaches construction costs the owner most. The EPCM's exposure is often the cost of redoing its own work, up to the cap, while the construction contractor's variation and the delay sit with the owner. On the budget estimate and the duration, a 2008 Mayer Brown comparison of EPC and EPCM contracts warns that "the Owner may struggle to establish a real loss, however negligent the EPCM contractor may have been".

There's an earlier conflict too. I found no published study on it, so take this as my view. The firm that writes the study estimate the board approves is sometimes bidding for the EPCM that follows. A lower estimate makes approval more likely, and approval puts that firm in line for the work.

A large EPCM may also run its own estimate reviews and benchmark against comparable projects. Fair enough. Those reviewers are still paid by the firm whose number they're testing, and the firm still wants the job.

In a 2020 article, Independent Project Analysis calls estimating and controls "a conflict of interest when performed solely by contractors without any checks". IPA's remedy is a strong owner team staffed across the core functions, project services included. A strong owner team still reports to the executive who took the project to the board, so the board needs a check from outside it as well.

In-House Checks Stay Quiet for a Reason

Keil and Robey's 2001 study of software projects shows why. In their interviews with IS auditors, a junior staff auditor described going to the executive VP who had championed a failing project for years and telling him to pull the plug as "career suicide". The auditor was the in-house check, and saw speaking up as the end of a career.

An owner's Project Director who sees trouble is in the same chair. An independent review that reports to the board gives that Project Director a second voice at the table, so they aren't left alone with the bad news.

Lenders Already Rely on a Second Opinion

A January 2026 FTI Consulting article describes lenders relying on independent technical advisers before a financial investment decision and again whenever the borrower asks for a drawdown. The article warns against "overreliance on borrower and/or contractor-provided information without independent and qualified verification". A junior funding its build from equity may have no lender's adviser in the room at all. That board has the widest gap.

A reviewer has a stake too. It wants to be asked back, and a red finding can mean more work. The board can see that stake and manage it.

In my view independence rests on three things. The reviewer is appointed by and reports to the board or its audit and risk committee, outside the management line. The fee doesn't depend on the answer. And the reviewer didn't prepare or control what it now tests. Flyvbjerg and his co-authors called for forecasts to face "expert and independent peer reviews". The board should read that review before the money goes out.

Three Questions Before the Capital Goes In

  • Who checked this estimate, and who appointed them?
  • Added together, when do the contractors' own programmes finish?
  • Has anyone outside the project tested the contingency against how comparable projects have actually finished?