AACE International's recommended practice for estimating mining and mineral processing projects, 47R-11, contains one sentence that every study cover should be read against. Project definition, it says, "is not the sole determinate of accuracy; risk analysis is required for that purpose."

I'd test every range against it. A range of plus or minus 15 per cent on a scoping, pre-feasibility or feasibility study is a claim about how far the final cost can fall from the estimate. If there's no quantitative risk analysis of this estimate behind it, a board has nothing to check the claim against. The board, and anyone lending or investing on the strength of the study, should see that analysis.

What the Benchmark Says

47R-11 is "a guideline, not a standard". It recommends, as "best industry practice to manage investment risk", that a mining feasibility study capital estimate be treated as Class 3, which AACE describes as the "basis for full funding". A Class 3 estimate sits on 10 to 40 per cent project definition. Its typical accuracy at 80 per cent confidence runs from minus 10 to minus 20 per cent on the low side and from plus 10 to plus 30 per cent on the high side (Exhibit 1).

AACE's Class 3 high end runs further than its low end Range bars on a per cent scale from minus 25 to plus 35. AACE Class 3, the class 47R-11 recommends for a mining feasibility study: low end between minus 10 and minus 20 per cent, high end between plus 10 and plus 30 per cent, at 80 per cent confidence, measured from the estimate after contingency. Illustrative cover range from the paper: minus 15 to plus 15 per cent. Zero is the estimate after contingency, typically set at a 50 per cent chance of overrun; Class 3 rests on 10 to 40 per cent project definition; an actual project can still fall outside the range. Source: AACE International RP 47R-11, Rev. 7 August 2020, pages 4 to 5 and Table 1. EXHIBIT 1 AACE's Class 3 high end runs further than its low end Typical accuracy at 80% confidence, per cent variation of actual cost from the estimate after contingency AACE Class 3, the class 47R-11 recommends for a mining feasibility study Low end: −10% to −20% High end: +10% to +30% Illustrative cover range: plus or minus 15% −15% +15% −20% −10% 0 +10% +20% +30% Note: 0 is the estimate after contingency, typically set at a 50% chance of overrun. Class 3 rests on 10% to 40% project definition. An actual project can still fall outside the range. The cover range is illustrative, from the paper. Source: AACE International RP 47R-11 (Rev. 7 August 2020), pp. 4 to 5 and Table 1.
Exhibit 1 Data
Exhibit 1. AACE's Class 3 high end runs further than its low end. Typical accuracy at 80% confidence, per cent variation of actual cost from the estimate after contingency. Note: 0 is the estimate after contingency, typically set at a 50% chance of overrun. Class 3 rests on 10% to 40% project definition. An actual project can still fall outside the range. The cover range is illustrative, from the paper. Source: AACE International RP 47R-11 (Rev. 7 August 2020), pp. 4 to 5 and Table 1.
RangeLow EndHigh End
AACE Class 3, the class 47R-11 recommends for a mining feasibility study-10% to -20%+10% to +30%
Illustrative cover range: plus or minus 15%-15%+15%

AACE measures the ranges from the estimate "after application of appropriate contingency", typically set at a 50 per cent chance of overrun, so a cover that doesn't state the contingency can't be placed in the band at all. It also says the ranges don't stop an actual project landing outside them.

JORC leaves the number to the industry. The 2012 Code defines its study stages by purpose and confidence, and its study clauses put no percentage on accuracy. Writing in the AusIMM Bulletin in 2015, Peter McCarthy of AMC said "there is no agreed standard for quality or accuracy".

The ASX has made a related point. Its 2016 interim guidance on scoping studies warns that reporting results "as a single specific figure may mislead investors by conveying a degree of accuracy, rigour or certainty" that a low-level study can't support. In my view a tidy symmetric range on a later study can give the same false comfort when nobody has tested it.

When the Scope Changes After the Study

Liontown Resources' Kathleen Valley lithium project shows how a range can travel further than the estimate behind it. Its November 2021 definitive feasibility study priced pre-production capital at A$473 million for a 2.5 million tonne a year plant. When Liontown's board approved development in June 2022 at A$545 million, the company said the increase was "driven primarily by optimisation and expansion of the FEED scope" and "general cost escalation", and that the revised figure remained "consistent with" the study's plus or minus 15 per cent "tolerance for accuracy".

The scope kept growing. In early 2023 start-up capacity went to 3 million tonnes a year and Liontown reported a constrained labour market and some tenders more than 30 per cent higher. By September 2023 it had brought the 4 million tonne step forward by two years and adopted a "two orebodies, one mine" strategy. The estimate to first production was then A$951 million, in real terms and including capitalised mining costs (Exhibit 2).

At Kathleen Valley, each capital estimate priced a different scope and market Four dated steps disclosed by Liontown Resources, three of them with a capital figure and its basis. November 2021 DFS: A$473 million pre-production capital, 2.5 Mtpa plant. June 2022 board approval: A$545 million pre-production capital; FEED scope optimised and expanded, general cost escalation; Liontown said this was consistent with the DFS plus or minus 15 per cent tolerance for accuracy. January 2023 project update: start-up capacity raised to 3 Mtpa; some tenders more than 30 per cent higher. September 2023 project update: A$951 million to first production, different basis, real and including capitalised mining costs; 4 Mtpa brought forward two years; two orebodies, one mine strategy. Liontown disclosed each change and its reasons. Sources: Liontown Resources ASX announcements of 29 June 2022, 20 January 2023 and 29 September 2023. EXHIBIT 2 At Kathleen Valley, each capital estimate priced a different scope and market Capital estimate at each disclosure, A$m, with its basis and the scope or market change Nov 2021 DFS A$473m pre-production capital 2.5 Mtpa plant Jun 2022 Board approval A$545m pre-production capital FEED scope optimised and expanded, general cost escalation Liontown said this was "consistent with" the DFS ±15% "tolerance for accuracy" Jan 2023 Project update Start-up capacity raised to 3 Mtpa Some tenders more than 30% higher Sep 2023 Project update A$951m to first production Different basis: real, including capitalised mining costs 4 Mtpa brought forward two years, "two orebodies, one mine" Note: Liontown disclosed each change and its reasons. Source: Liontown Resources ASX announcements of 29 June 2022 (p. 2), 20 January 2023 (pp. 2 to 3) and 29 September 2023 (pp. 1 to 3).
Exhibit 2 Data
Exhibit 2. At Kathleen Valley, each capital estimate priced a different scope and market. Capital estimate at each disclosure, A$m, with its basis and the scope or market change. Note: Liontown disclosed each change and its reasons. Source: Liontown Resources ASX announcements of 29 June 2022 (p. 2), 20 January 2023 (pp. 2 to 3) and 29 September 2023 (pp. 1 to 3).
DateEventCapital Estimate and BasisScope and Market
Nov 2021DFSA$473m pre-production capital2.5 Mtpa plant
Jun 2022Board approvalA$545m pre-production capitalFEED scope optimised and expanded, general cost escalation. Liontown said this was "consistent with" the DFS ±15% "tolerance for accuracy"
Jan 2023Project updateNo capital figure shownStart-up capacity raised to 3 Mtpa. Some tenders more than 30% higher
Sep 2023Project updateA$951m to first production. Different basis: real, including capitalised mining costs4 Mtpa brought forward two years, "two orebodies, one mine"

Liontown disclosed each change and its reasons, and nothing in its record suggests the study was labelled above its engineering. I draw one lesson from it. An accuracy range describes the scope that was estimated and the risks that were analysed. Once the scope or the market moves, a board should ask for the range to be estimated again before it relies on one.

Ground Risk Has to Be in the Analysis

The largest uncertainties on a mine often sit underground. In July 2019 Rio Tinto put development capital for the Oyu Tolgoi underground project at $6.5 billion to $7.2 billion, up from the $5.3 billion previously disclosed, and reported a delay of 16 to 30 months against the original feasibility study guidance of 2016. Rio said "there may be some stability risks identified with the approved mine design".

The public record doesn't say what a review would have changed there, and I won't guess. What a board can ask of any study is how its risk analysis treated geotechnical uncertainty in the approved design, and whether the schedule carried that uncertainty as well as the cost.

Where the Lender's Engineer Doesn't Reach

Where a project borrows, the lenders can appoint their own independent engineer. SRK, for example, was engaged in 2011 by the potential lenders to the Kwale mineral sands project in Kenya as Independent Engineer and reviewed the feasibility study before the loan facility was signed.

That review arrives with the debt. A board that approves a project before its debt is arranged, a company raising equity on a fresh study and a junior with no lender yet all take the study's range without it. In my view that's where a board carries the most risk, especially when the study was underfunded or run to a compressed timetable to meet a funding date. That's a point about circumstances, and I make no criticism of the teams working in them.

For a Managing Director, that means preparing. A lender's engineer, when one arrives, is likely to ask questions like these. Having the answers ready, with the risk analysis on the table, is cheaper than finding the gap in due diligence.

Three Questions Before the Range Is Relied On

  • Was the quantitative risk analysis run on this estimate, or was a factored range applied after it was finished?
  • How does the analysis treat geotechnical and other ground risk?
  • What has changed in scope or market since the range was set?

Start with the first one. If the range came from the terms of reference, it's the target the team was set, and the risk analysis still needs doing.

At Meridian Advisory we check, independently, that the cost and the date behind a project are real before the capital is committed, or when the forecast is reset during the build.

I'll be at Mines and Money London from 1 to 3 December. If a study's range is about to carry a board decision or a raise, find me there and we'll talk it through.