A P50 cost is the figure the project has an even chance of coming in under. A P80 cost is the figure it has an eight in ten chance of coming in under. The same applies to dates.

Both come from one model of the range of outcomes, built from the estimate, the schedule and the risks.

What the Gap Shows

When P50 and P80 sit far apart, the team still has a lot it can't pin down. A board shown only one number can't see that, and can't ask whether a gap of that size is believable for a project at this stage.

When the Model Is Weak

The P80 comes out of the model, so a thin estimate or a schedule with no logic gives a precise-looking P80 on a weak base. A reviewer tests the basis of the estimate and the quality of the schedule before reading anything into the P80.

What to Ask

  • Which number is the budget, and which number is the board being asked to approve?
  • What drives the gap between P50 and P80, and who owns those risks?
  • Was the range built from the project's own risks, or from a standard spread?
  • Does the schedule have its own P50 and P80, and do they line up with the cost?