Contingency covers the cost of things inside the scope that the estimate can't yet pin down: quantities that will move, prices that will change, design that isn't finished. Major scope changes usually sit outside it.
Percentage or Evidence
A percentage allowance is quick and familiar. Ten per cent on a well-defined project and ten per cent on an early, uncertain one give the two projects very different chances of coming in on budget. The explainer below shows how far apart they can sit.
What a Percentage Allowance Hides
The same allowance on two illustrative projects. Move the slider to change the allowance.
- Well-Defined Project
- Early or Uncertain Project
| Allowance | Well-Defined Project | Early or Uncertain Project |
|---|---|---|
| 0% | P17 | P21 |
| 5% | P44 | P30 |
| 10% | P73 | P41 |
| 15% | P91 | P52 |
| 20% | P98 | P63 |
| 30% | P99 | P79 |
| 40% | P99 | P90 |
Illustrative. Both cost ranges are invented for this explainer. On a real project the range comes from your own estimate, schedule and risk register.
An evidence-based allowance starts from the estimate, the schedule and the risk register. It models the range of outcomes and sets contingency at a stated confidence level. The result can be higher or lower than the percentage, and the risks driving it are ranked so the team knows what to manage.
Where Contingency Goes Wrong
- It's set once and never revisited as the design matures.
- It pays for new scope.
- Schedule risk is left out, so nothing is held for the cost of delay.
- It's reported as one number, with no confidence level.
What to Ask
- How was the figure derived, and what confidence level is it set at?
- What would it need to be at P80?
- Who can draw on it, and how is that recorded?
Related Service
Probabilistic cost and schedule risk, with contingency set from the project's own risk evidence.