A capital decision gate is the point where the next tranche of money is approved, stopped or sent back. Each gate asks one question, and the project has to bring the evidence to answer it.
Signs a Gate Has Stopped Working
- Every project that reaches the gate passes it.
- The criteria aren't written down, or were written after the decision.
- Nobody at the table can stop the project or send it back.
- The pack arrives too late to be read.
How a Gate Sequence Works
Pick a gate.
Concept
Is there a project worth studying?
The project shows the business need, the options considered, an order of magnitude cost and a reason to spend money on a study.
Pre-feasibility
Which option goes forward, and why?
The options are compared on the same basis. The pack names the preferred option, the main risks and the cost and time to reach the next gate.
Feasibility
Is the chosen option defined well enough to fund?
The pack holds the estimate and its basis, a logic-linked schedule, the risk analysis, the contracting strategy and the plan for the owner's team.
Investment Decision
Should the capital be committed, at this cost and date?
The board needs the cost and the date at stated confidence levels, an independent review, funding in place and a delivery team ready to go.
Execution and Close
Is the project delivering what was approved, and what did we learn?
The project reports progress against the approved baseline and the cost of the changes, and ends with a close-out review.
A typical sequence for a mining or infrastructure project. The gates, their names and what each needs are set to fit each organisation.
A company running its first build can start with fewer gates than the five shown above, each with written criteria, and a person or committee with the authority to stop the project. More gates can follow when a second project starts.
What to Ask
- Are the criteria for the next gate written down, and was the last gate tested against them?
- Who can stop the project or send it back, and has that ever happened?
- Does the pack reach the decision makers in time to be read?
Related Service
A gate system we install and run, so capital decisions rest on tested information.